Software built by planners, for planners

Our consultancy runs on P6 Schedule Analytics, a platform we designed and built. Upload a Primavera P6 XER or XML and in minutes see whether the programme will stand up to scrutiny. Try the free demos below.

P6 Schedule Analytics · 17 modules

Every check we would run by hand, automated

Reads Primavera P6 XER and P6 XML files up to 400 MB. Load earlier updates or a baseline to unlock trend, submission and delay analysis.

Software + expertise

Use the software yourself, or let us use it for you

The platform tells you what is wrong with a programme. Our planners tell you why it matters contractually and fix it. Many clients start with the software and call us in when a submission is due or a dispute looms.

PlanForIndicative price
FreeEvaluation: one project, DCMA summary£0
ProfessionalPlanners: DCMA, Insights, EVM, Repair XER£32.50 / user / month
TeamAdds forensic, QSRA, NEC4, time-chainage£99 / user / month (min 3)
Project passAll modules, one project, 90 days£149 one-off
ConsultancyOur planners use the platform on your projectFixed fee / day rate

Prices exclude VAT and are taken from planassure.co.uk/pricing. [Confirm before launch]

Free demo · runs in your browser

QSRA Monte Carlo simulator

Edit the network, three-point estimates and risk register, then run thousands of iterations. Each iteration performs a full CPM forward and backward pass, as in a real QSRA.

Programme & risk inputs

ACTIVITIES: durations in days. Predecessors are finish-to-start, comma-separated.

IDNamePred.MinMLMax

RISK EVENTS: probability % and impact (days) added to the activity.

RiskP%OnMinMLMax

Completion distribution & S-curve

Risk drivers (tornado)

3D convergence view: watch the distribution settle as iterations accumulate

Drag to rotate

Demonstration model only. A real QSRA starts with a schedule health check, facilitated risk workshops, correlation between activities, and a calibrated risk register run on the full P6 network.

Free demo

Earned value & earned schedule calculator

Enter cumulative PV, EV and AC by period (£k). The last PV value is taken as the budget at completion (BAC). Leave future EV and AC blank.

PeriodPVEVAC
Formulae used

CV = EV − AC · SV = EV − PV · CPI = EV ÷ AC · SPI = EV ÷ PV
ES = C + (EV − PVC) ÷ (PVC+1 − PVC) · SPI(t) = ES ÷ AT · IEAC(t) = PD ÷ SPI(t)
EAC = BAC ÷ CPI (and AC + (BAC − EV); AC + (BAC − EV) ÷ (CPI × SPI(t)) for the range)
TCPI = (BAC − EV) ÷ (BAC − AC) · VAC = BAC − EAC

Want this on your real programme?

Send an XER. We'll run the full analysis and walk you through the results.